These are the different Statuses available in the TMS. The status of a document, target and phase will trigger different responses in the workflow and interactions between applications in the TMS. Used properly, they enable automation and powerful functionality in integrations.
Status Types
Status | State | Document | Target | Phase/Task |
---|
Ready | Active | The document is ready if: - The phase has not progressed past the pre-translation steps (Leverage TM and Machine Translation).
| The target is considered ready if: - The document has first been uploaded into the Project app and its phases have not begun.
| A phase is considered ready if: - It is the first phase in a target that has just started or if the phase prior is complete.
|
---|
In Progress | Active | The document is in progress if: - The pre-translation steps have been completed.
- Work has begun on human steps (Translation, review).
| Targets are in progress if: - Any of their phases are in progress.
- Or if some of their phases are complete.
| A phase is considered in progress if: - It's progress is greater than 0%.
|
---|
At Risk | Active | The document is at risk if: - The workflow has not been completed for all targets.
- The Document Due Date is approaching.
| Targets are at risk if: - Any of their phases are incomplete and the due date is approaching.
| A phase is at risk if: - It has not been marked complete and the due date is approaching.
|
---|
Past Due | Active | The document is Past Due if: - One or all targets have not completed their workflows and the document has passed the Document Due Date.
| Targets are past due if: - Some or all of their phases have not completed the workflow and it has passed the Target Due Date.
| A phase is past due if: - It has not been marked complete and the phase due date has passed.
|
---|
Waiting | Inactive | NA | NA | A phase is waiting if: - The phases prior are still in progress.
|
---|
Waiting (At Risk) | Inactive | NA | NA | A phase is waiting (at risk) if: - The phase is approaching the due date but is still not available to begin work.
|
---|
Waiting (Past Due) | Inactive | NA | NA | A phase is waiting (past due) if: - The phase has passed the due date but is still not available to begin work.
|
---|
Skipped | Inactive | NA | NA | A phase can be skipped if: - It is not in an inactive state.
- If the phase has not started.
|
---|
Canceled | Inactive | A document can be canceled if: - It is not in an inactive state.
- If the document is in progress, it can still be canceled.
| A target can be canceled if: - It is not in an inactive state.
- If the target is in progress, it can still be canceled.
| A phase can be canceled if: - It is not in an inactive state.
- If the phase has begun, it can still be canceled.
|
---|
Completed | Inactive | A document is completed if: - All targets in the document have completed the workflow before the due date.
| A target is completed if: - All phases within the target have been completed before the due date.
| A phase is complete if: - The phase has reached 100% status and has been marked complete.
|
---|
Late | Inactive | A document is late if: - All of the targets are completed, but one or more targets were completed after the due date.
| Targerts are marked late if: - All of their phases have been completed, but one or more of the phases were completed after the due date.
| A phase is late if: - It has been completed after the due date.
|
---|
Canceling vs. Skipping a Phase
Only phases can be Canceled or Skipped. Documents and Targets can only be canceled. However, a canceled Document or Target will have different affects on the phase depending on the status of the phase.
- Canceling a document will cancel every target that has not completed its workflow. Canceling a target will:
- Skip phases that have not yet been started.
- Mark every phase that is In Progress as Canceled.
- Leave Completed phases as Complete.